FROM DEMOLITION TO TRANSFORMATION
There has been significant progress on site, bringing in a wave of excitement as we officially commenced construction of our new High School.
- ELC precinct works completed, with fully upgraded outdoor learning and play spaces now fully operational and being enjoyed by students.
- New Gate 4 access opened for ELC families, improving campus access and supporting future traffic and drop-off plans for the redeveloped High School.
- New Gate 4 security infrastructure that will provide enhanced physical and electronic protection, creating a safer and more resilient campus.
- Brender Moss Library demolition completed, creating the footprint required for the construction of the new High School.
- Demolition works completed efficiently and with minimal disruption, supported by dust, noise and traffic management measures, and consideration for Year 12 trial exams.
12
JUN 2026
MAJOR WORKS CONTRACT SIGNED
- This is a fixed price contract, locking in the full scope of the development.
- Allows us to commit to build successive portions of the development, as our fundraising continues to progress.
- Reaching this point has required the dedication, commitment and hard work of many who have led this effort, as well as the generosity and unwavering support of you, our Moriah community.
- Read more here.